12.32.120 Concurrent review with other required permits.
This section is included in your selections.
Applicants are strongly encouraged to complete site plan review prior to submittal of an application for any construction-level development permits such as, but not limited to: building, right-of-way, utility, and grading permits. No construction-level development permits shall be issued prior to completion of site plan review, except in the circumstances described in BMC 12.32.020(E) for which a separate site plan review is not required. Applicants submitting applications for any construction-level development permits before completing site plan review do so at their own risk. (Ord. 2370 § 3, 2021; Ord. 2269 § 4, 2018).