A. Envelope inspections shall include the following:

1. Wall insulation inspection: to be made after all wall insulation and air vapor retarder sheet or film materials are in place, but before any wall covering is placed.

2. Glazing inspection: to be made after glazing materials are installed in the building.

3. Exterior roofing insulation: to be made after the installation of the roof insulation, but before concealment.

4. Slab/floor insulation: to be made after the installation of the slab/floor insulation, but before concealment.

B. Mechanical system inspections shall include the following:

1. Mechanical equipment efficiency and economizer: to be made after all equipment and controls required by this code are installed and prior to the concealment of such equipment or controls.

2. Mechanical pipe and duct insulation: to be made after all pipe, fire suppression piping and duct insulation is in place, but before concealment.

C. Lighting equipment and controls inspections shall include the following:

1. Lighting equipment and controls: to be made after the installation of all lighting equipment and controls required by this code, but before concealment of the lighting equipment.

2. Motor inspections: to be made after installation of all equipment covered by this code, but before concealment. (Ord. 2344 § 1 (Exh. A), 2021; Ord. 1986 § 1, 2007; Ord. 1926 § 4, 2004).