It is unlawful for any person to cover or backfill any storm drainage side sewer, private storm sewer or lateral without having called for and received an inspection, testing and approval by the public works director. The applicant shall notify the public works department and request an inspection at least 24 hours before the scheduled inspection. The storm drainage side sewer permit shall be available on site at the time of the inspection. The permit fee shall include the cost of inspection except for the following:

A. Inspections during hours other than public works business hours;

B. Inspections requested by a contractor during storm side sewer installation requiring deep cuts, extremely wet soil conditions or when backfill is placed on pipe prior to test;

C. Call back resulting from poor workmanship or failure to comply with the code. (Ord. 2023 § 1 (Exh. A), 2009; Ord. 1634 § 1, 1996).