A. General. Before applying for a shoreline substantial development permit, shoreline conditional use permit, or shoreline variance under this chapter, the applicant shall attend a pre-application conference with the city consistent with the provisions of BMC 11.06.001.

B. Scheduling. The department of community development shall schedule the pre-application conference no more than 45 calendar days following the filing of a written request for a pre-application conference.

C. Submittal. Pre-application submittals shall include the following documentation:

1. Site plan showing the proposed development in relation to the shoreline;

2. Written description of the proposal and related improvements;

3. Other information as identified on the submittal form provided by the community development department; and

4. Pre-application conference fee.

D. Purpose. The purpose of the pre-submittal meeting is for the shoreline administrator to provide a general summary of the procedures and timelines to be used to process the application; references to the relevant code provisions or development standards which may apply to the approval of the application, as preliminarily identified at the pre-application conference; identify general code requirements.

E. Time Limits. The city will not process an application under this chapter unless the applicant attended a pre-submittal meeting under this section, regarding the proposal for which application is made, within the six months immediately prior to the date the application is submitted. (Ord. 2112 § 3 (Exh. C), 2013).